What is the Section 20 major works threshold?

The Section 20 threshold means a landlord must consult before works costing any one leaseholder more than £250, or the amount they can recover is capped.

Last updated 2 min readWritten by the Hive United team
The short answer

The major works threshold is the cost level that triggers Section 20 consultation. If qualifying works would cost any one leaseholder more than £250, the landlord must consult first. If they don't, and the tribunal doesn't grant dispensation, the amount recoverable from each leaseholder for those works is capped at £250.

General information only, not advice. England and Wales. Scotland and Northern Ireland have different rules.Read more
General information only, not advice. This page describes the law in England and Wales as at 7 November 2026. It isn't legal, financial or professional advice. No solicitor has checked it, and it may be incomplete, out of date or wrong for your situation. Don't rely on it to make decisions. Check your lease and the official sources linked here, and get independent advice from a solicitor or the Leasehold Advisory Service (LEASE). Hive United accepts no responsibility for any action you take, or don't take, based on it. Read our full disclaimer.

Written by the Hive United team.

Is the £250 threshold per flat or for the whole building?

It is per leaseholder. The test is whether the relevant contribution of any one tenant would be more than £250, not whether the whole project costs more than £250. So a £3,000 job shared between 10 flats equally is £300 each and crosses the threshold, while the same job shared by 20 flats is not.

Swipe sideways for all 5 columns

Example Total cost Flats sharing equally Each share Over the threshold?
Door entry repair £3,000 10 £300 Yes
Door entry repair £3,000 20 £150 No
Roof renewal £60,000 15 £4,000 Yes

If shares are unequal under the leases, the flat with the biggest share decides whether the threshold is crossed.

What happens if the landlord doesn't consult?

Under section 20 of the Landlord and Tenant Act 1985, a landlord who carries out works over the threshold without consulting, or without dispensation from the tribunal, can only recover the threshold amount from each leaseholder for those works. In England and Wales that is £250 per leaseholder.

Is there a different threshold for long contracts?

Yes. Long-term agreements of more than 12 months, such as cleaning, lift maintenance or management contracts, have their own threshold: consultation is needed if any leaseholder's contribution would be more than £100 in any accounting period. Our qualifying long-term agreement entry explains that test.

Can the threshold be avoided by splitting the works?

Consultation is about the works as a whole. Splitting one project into small jobs to keep each below £250 can be challenged, and the tribunal looks at the facts. If you think a job has been split, ask in writing how the works were scoped and priced.

Sources

Sources consulted on 7 November 2026. Official sources can change, so check the latest version:

Disclaimer

This page is general information only. It isn't legal, financial or professional advice, and no solicitor has checked it. It may be incomplete, out of date or wrong for your situation, so don't rely on it to make decisions. Check your lease and the official sources linked above, and get independent advice from a solicitor or the Leasehold Advisory Service (LEASE). Hive United accepts no responsibility for any action taken, or not taken, based on this page. Read our full disclaimer.