Blog · Section 20

Major works bill higher than the estimate?

A final major works bill can exceed the Section 20 estimate, but costs must still be reasonable and demanded in time. What to check and ask before paying.

Last updated 3 min readWritten by the Hive United team
18months
Is usually how long a landlord has to demand costs or warn you of them
The short answer

A final major works bill can be higher than the estimate in the Section 20 notices, but the extra must still be justified. Under section 19 of the Landlord and Tenant Act 1985, you only pay costs that were reasonably incurred for work of a reasonable standard. The landlord also has to demand the costs, or warn you about them, within 18 months of incurring them.

General information only, not advice. England and Wales. Scotland and Northern Ireland have different rules.Read more
General information only, not advice. This page describes the law in England and Wales as at 14 November 2026. It isn't legal, financial or professional advice, and no solicitor has checked it. It may be incomplete, out of date or wrong for your situation, so don't rely on it to make decisions. Check your lease and the official sources linked here, and get independent advice from a solicitor or the Leasehold Advisory Service (LEASE). Hive United accepts no responsibility for any action taken, or not taken, based on it. Read our full disclaimer.

Written by the Hive United team.

Is the Section 20 estimate a cap?

Not as such. Consultation under section 20 is about the process: if the landlord follows it, or the tribunal grants dispensation, the cost isn't limited to £250 per leaseholder. But the costs you pay are still limited by section 19 to what was reasonably incurred. An increase needs a good reason, such as problems that only appeared once work started.

If the works changed a lot from what was consulted on, ask the landlord whether it considered further consultation or dispensation.

What should you ask for?

The final account, showing the contract sum, each variation and why it was needed. Ask for the contract administrator's or surveyor's reports, any instructions for extra work, the final certificate and copies of the invoices, so you can compare the final cost with the estimate line by line.

Ask for Why it helps
Final account with variations Shows where the extra cost came from
Reasons for each variation Tests whether it was reasonably incurred
Notices sent during the works Shows whether you were warned of increases
Date costs were incurred Checks the 18-month rule

Our major works clarification questions help you ask, and Section 20 surprises covers other common problems.

What is the 18-month rule?

Section 20B says that if costs were incurred more than 18 months before you're asked to pay them, you don't have to pay, unless within those 18 months the landlord told you in writing that the costs had been incurred and you would have to contribute. Check the dates on the invoices and on any notices.

Can you challenge the final bill?

Yes. If you think the extra costs weren't reasonably incurred, you can ask the First-tier Tribunal (Property Chamber) in England to decide what is payable under section 27A. In Wales, the Residential Property Tribunal Wales decides. Pay what you accept is due while you challenge the rest.

The Section 20 guide and major works entry explain the consultation stages.

The statement of estimates shows the figures you were consulted on, and our completion checklist helps you record whether the work was finished properly.

Frequently asked questions

Do I have to pay the full final bill straight away?

Check your lease for when payment is due. You can pay what you accept is reasonable while you ask questions about the rest.

Does the landlord need to consult again for extra costs?

There's no automatic rule that every increase needs fresh consultation. If the work itself changed, ask the landlord whether further consultation or dispensation was considered.

Can leaseholders challenge the bill together?

Yes. Several leaseholders can raise the same questions, and a joint approach can share the work of checking the final account.

What if I paid in advance and the cost went down?

Advance payments must be no more than is reasonable, and the difference should be adjusted once the costs are known, by repayment or credit.

Sources

Sources consulted on 14 November 2026. Official sources can change, so check the latest version:

Disclaimer

This page is general information only. It isn't legal, financial or professional advice, and no solicitor has checked it. It may be incomplete, out of date or wrong for your situation, so don't rely on it to make decisions. Check your lease and the official sources linked above, and get independent advice from a solicitor or the Leasehold Advisory Service (LEASE). Hive United accepts no responsibility for any action taken, or not taken, based on this page. Read our full disclaimer.

Find your building

See if your neighbours have started a space. You can join with a code, or start one for your block.

Find your building