No. The Section 20 consultation rules in England set no expiry date for a notice of intention or a statement of estimates. A delay between stages doesn't by itself make the consultation invalid. But if the works, the price or the contractor change a lot while the project stalls, the earlier consultation may no longer cover what's done.
General information only, not advice. England and Wales. Scotland and Northern Ireland have different rules.Read more
Written by the Hive United team.
Is there a time limit between Section 20 stages?
Not a fixed one. The Service Charges (Consultation Requirements) (England) Regulations 2003 set a 30-day period for observations after each notice, but they don't say how soon the next stage must follow. A landlord can give a notice of intention, then take months to get estimates. Leaseholders can still ask why.
For most major works, Part 2 of Schedule 4 to the Regulations sets the stages:
What the landlord What the landlord doesTime Time for leaseholders
| Stage | What the landlord does | Time for leaseholders |
|---|---|---|
| Notice of intention | Describes the works and invites observations and nominations | 30 days |
| Statement of estimates | Sets out at least two estimates and invites observations | 30 days |
| Notice of reasons | Explains the choice of contractor, unless it was the lowest estimate or a leaseholder's nominee | Given within 21 days of the contract |
What if the works change after a long delay?
Ask what has changed. Consultation is about the works described in the notices and the estimates you were shown. If the scope, the price or the contractor is now very different, the earlier consultation may not cover it, and the landlord may need to consult again or ask the tribunal for dispensation. Put your questions in writing.
Useful questions include whether the specification has changed, whether the estimates are still valid, and when work is now due to start. Our post on Section 20 surprises covers other common problems.
Can old estimates still be used?
The Regulations don't set a shelf life for estimates, but contractors often only hold a price for a set period. If the contractor's price has gone up, ask the landlord whether it plans to use the same estimate, get new ones or consult again. Compare what you're finally asked to pay with what was in the statement of estimates.
What if the landlord skips consultation?
Without consultation or dispensation, the landlord can only recover £250 from each leaseholder for qualifying works. The tribunal can grant dispensation under section 20ZA of the Landlord and Tenant Act 1985 if it's satisfied that is reasonable. Leaseholders can object to a dispensation application and explain any prejudice they suffered.
See the dispensation entry for how applications work.
Does the 18-month rule apply to delayed works?
Yes, once the costs are incurred. Under section 20B of the 1985 Act, a cost incurred more than 18 months before you're asked to pay it usually can't be recovered unless you were told in writing in time. A long delay before the work starts doesn't trigger the rule; delay in billing after the cost is incurred can.
The charge also has to be reasonable under section 19, and the work done to a reasonable standard.
What should leaseholders do while works are delayed?
Keep every notice and the dates you received them, and ask the managing agent for a timetable in writing. If you made observations, check the landlord's response to them. If anything changes, ask whether a new consultation is planned. These rules apply in England; Wales has its own consultation regulations, which are very similar.
The Section 20 consultation guide explains each stage, and the notice of intention entry covers the first notice in more detail.
Frequently asked questions
Does a Section 20 notice become invalid after a year?
The 2003 Regulations set no expiry date. What matters is whether the works and price still match what leaseholders were consulted on.
Can the landlord use the same estimates years later?
The Regulations don't stop it, but the price may have changed. Ask whether the contractor still holds the estimate and whether new consultation is planned.
How long do leaseholders get to comment?
30 days from the date of each notice, called the relevant period in the 2003 Regulations.
What can the landlord charge without consultation?
No more than £250 per leaseholder for qualifying works, unless the tribunal grants dispensation.
Sources
Sources consulted on 17 November 2026. Official sources can change, so check the latest version:
- Landlord and Tenant Act 1985, section 20 (limitation of service charges: consultation requirements)
- Service Charges (Consultation Requirements) (England) Regulations 2003 (SI 2003/1987)
- Service Charges (Consultation Requirements) (England) Regulations 2003, regulation 2 (relevant period of 30 days)
- Service Charges (Consultation Requirements) (England) Regulations 2003, Schedule 4, Part 2
- Landlord and Tenant Act 1985, section 20ZA (consultation requirements: supplementary)
- Landlord and Tenant Act 1985, section 20B (limitation of service charges: time limit on making demands)
- Landlord and Tenant Act 1985, section 19 (limitation of service charges: reasonableness)
Disclaimer
This page is general information only. It isn't legal, financial or professional advice, and no solicitor has checked it. It may be incomplete, out of date or wrong for your situation, so don't rely on it to make decisions. Check your lease and the official sources linked above, and get independent advice from a solicitor or the Leasehold Advisory Service (LEASE). Hive United accepts no responsibility for any action taken, or not taken, based on this page. Read our full disclaimer.